Your first 90 days: new program

The logic of the sequence for a brand-new program — four phases, 90 days to launch. Your inputs save automatically and export to PDF.

Auto-save on
Unlocked LabsBreaking Down Barriers Toolkit
Worksheet · BDB-PM-01A
Rev. 2026 — Templates and Tools
Not yet saved
Quick start — Version A

Your first 90 days: new program

This is an orientation, not a project plan. It gives you the logic of the sequence — what to do in what order and why — so you can move through implementation without missing critical steps. For the detailed task work, use the tools linked at each phase. Expect 12 to 18 months from concept to first enrolled student.

TrackNew program from scratch — four phases.
Time90 days to launch (12–18 months concept to first student).
OutputA phase-by-phase progress record you can share with your team.
Contents
1
Know Your Ground
2 sections · not started
2
Build Your Coalition
1 sections · not started
3
Plan the Technology
1 sections · not started
4
Build the Infrastructure
1 sections · not started
5
Rules & progress tracker
3 sections · not started
01
Weeks 1–3

Know Your Ground

0

Before you start

New program from scratch — four phases, 90 days to launch. This is an orientation, not a project plan. It gives you the logic of the sequence so you can move through implementation without missing critical steps. For the detailed task work, use the tools linked at each phase. Expect 12 to 18 months from concept to first enrolled student.

Program
Facility
Target launch
1

Phase 1 — Know Your Ground

You cannot design a program you do not understand yet. This phase is about information gathering — not planning, not pitching, not selecting technology. Resist the urge to move faster. Key rule: Do not select technology during this phase. Programs that choose devices or platforms before understanding their infrastructure and student population consistently encounter avoidable problems.

Done when
Key tools: Needs Assessment Checklists · Stakeholder Mapping Worksheet · Delivery Model Decision Framework · Navigating Approval Chains Workbook.
02
Weeks 4–7

Build Your Coalition

2

Phase 2 — Build Your Coalition

Securing the human support your program needs before you ask for formal approval. Approvals from people who do not understand or believe in the program are fragile. Approvals from people you have brought along are durable. Key rule: Engage security before you engage the warden. A proposal that has not been reviewed by the security director will be sent back — and going around them damages momentum. Security directors who co-design security measures become advocates.

Done when
Key tools: Building Support · Objection Response Preparation Worksheet · MOU Template · Navigating Approval Chains Workbook.
03
Weeks 8–10

Plan the Technology

3

Phase 3 — Plan the Technology

Technology selection happens here — after you understand your context and have coalition support, not before. This sequencing is not arbitrary: programs that select technology in Phase 1 may regret it, because they end up designing around technology constraints rather than educational needs. Key rule: Get security approval for specific device models in writing before purchasing. Verbal approval is not sufficient. Test software behind the actual facility filtering system — vendor demos are not conducted inside correctional networks.

Done when
Key tools: Technology Selection Worksheet · Vendor Fit Checklist · Budget Calculator Tools · Data Sharing Agreement Guidance.
04
Weeks 11–13

Build the Infrastructure

4

Phase 4 — Build the Infrastructure

The physical and technical work of making the program real: configuring systems, training people, preparing students. This is where delays from earlier phases compound. Protect this time — it cannot be compressed without consequences. Key rule: If you are behind schedule, revise your launch date rather than compressing Phase 4. Compressing staff training, systems testing, and student orientation is how programs launch badly and spend months recovering.

Done when
Key tools: Ready to Launch Checklist · Setting Up Tech Accommodations · Data Collection Plan. ► Day 90: Launch. Your first cohort begins. Now begin the monthly reporting, quarterly review, and annual evaluation cycles.
05
Reference

Rules & progress tracker

5

Critical sequencing rules

These are the sequencing failures that appear most consistently in programs that launch badly. Do not do these things:

Do not select technology before completing the Needs Assessment — you end up designing around technology constraints rather than educational needs. The sequence in this guide is intentional.
Do not approach the warden before engaging security and IT — a proposal that has not been reviewed by security will be sent back. Going around the security director — even with warden support — damages the relationship you need to sustain the program.
Do not start procurement after all approvals are secured — device delivery takes 4 to 8 weeks minimum. RFP processes take 6 to 12 months. Start procurement conversations during Phase 2, not at the end of Phase 3.
Do not compress Phase 4 to make up for earlier delays — staff training, systems testing, and student orientation cannot be rushed without consequences. If you are behind, revise the launch date.
Do not launch without the Ready to Launch Checklist complete — every unchecked item is a problem you will deal with after students are enrolled, which is significantly harder to fix.
6

When you are behind

Note where you are stuck and the next action.

Stuck on…
Your next action
Approvals — the most common delay. Identify the specific person or body that has not moved. Ask your champion to make a call. Review the Navigating Approval Chains Workbook: stall vs. hard no.
Procurement — timelines are largely fixed once started; the error was usually starting late. Check whether cooperative purchasing or state contracts can accelerate the current purchase.
Infrastructure — usually a staffing issue (facility IT capacity or your own). Name the constraint explicitly. Can a vendor or consultant absorb some of the load temporarily?
Partnerships — sometimes the right answer is a direct conversation about whether the partnership is ready to proceed. See the Navigating Approval Chains Workbook for how to distinguish a stall from a hard no.
7

Progress tracker

Record actual completion, status, and any blocker for each phase.

Progress tracker
ActualStatusBlocker
Phase 1: Know Your Ground (target Wk 3)
Phase 2: Build Coalition (target Wk 7)
Phase 3: Plan Technology (target Wk 10)
Phase 4: Build Infrastructure (target Wk 13)
Launch (target Day 90)
Do not select technology before completing the Needs Assessment. The sequence in this guide is intentional.